December 4, 2024
(Wednesday)
Power Off: 8:00 AM
Power On: 5:00 PM
Duration (Hours): 9 Hrs
AFFECTED AREA:
Brgy. San Vicente Silangan and Sta. Maria Dao, Catanauan, Quezon. Brgy. Malaya, Gen. Luna, Quezon
REASONS:
Pole/Line relocation due to rehabilitation/reconstruction of roads at Doongan Ila. Catanauan, Quezon
November 5, 7, 9, 12, 14, 16 (NGCP), 19, 21, 23, 26, and 28, 2024
(Tuesday-Thursday-Saturday)
(Tuesday-Thursday-Saturday)
Power Off: 6:00 AM
Power On: 5:00 PM
Power On: 5:00 PM
Duration (Hours): 11 Hrs
AFFECTED AREA:
Brgy. Burgos, Cawayanin, Piña Ila. and Iba., Sampalok, Adia, Osmeña, Casasahan Ila and Iba. and Saguinsinan, Pitogo
REASONS:
Construction of 69kV line from Pitogo up to Agdangan and Restructure of Agdangan up to Padre Burgos 13.2kV backbone line in preparation for the commissioning of 15MVA Agdangan Substation.